How is the operation of the LNG full containment tank carried out?

Release time:

2022-12-15

LNG Full Containment TankHow are the related operations carried out?

1. Preparation before pressure regulation

1. Preparation of tools

Explosion-proof adjustable wrench, two sets of gloves, and two sets of protective equipment.

2. Work preparation

(1) Wear labor protection equipment, including anti-static clothing, anti-static shoes, safety helmets, etc.

(2) Check whether mobile phones, computers, and other devices that easily generate static electricity are placed in a safe area, whether the surrounding environment is safe, and whether it meets the operating conditions;

e6793d38-660f-4f27-ad38-b85dd487e64d.png

(3) Before entering the station, touch the static discharge facility with your hand to release static electricity;

(4) Check whether the explosion-proof wrench and other pressure regulation tools are fully equipped;

(5) Check whether the pressure gauge, level gauge, thermometer, combustible gas detector, and safety valve of the storage tank are in normal working condition.

(6) Check whether the pipeline valves, pressure gauges, and safety valves are in normal working condition.

(7) Prepare the explosion-proof tools to be used.

2.LNG Full Containment TankGas supply process:

1. Confirm that all gas supply valves of the storage tank, except for the root valve and emergency shut-off valve, are closed.

2. Open the liquid inlet valve and pressurized liquid valve and gas valve at the bottom of the storage tank, and check whether the valves before and after the pressurized vaporizer are open.

3. Open the low-temperature shut-off valve before the vaporizer, the normal temperature flange ball valve after the vaporizer, and open all valves of the pressure regulation system.

4.a. When the gas supply amount is less than 1000-2000 nm3/h, using the liquid from one storage tank is sufficient to meet the gas supply requirements;

5. Outflow:

(1) When the pressure of the storage tank rises above 0.15MPa higher than the outlet pressure, slowly open the liquid outlet valve to complete the gas supply operation.

(2) Record the number of the storage tank and the time when gas supply starts.

(3) Closely monitor the changes in the liquid level and pressure of the storage tank during the gas supply process, as well as the changes in the outflow rate and pressure.

3. LNG Full Containment Tank Self-pressurization Operation Procedure

1. During manual operation, open the valves: pressurized liquid phase valve, pressurized gas phase bypass valve, and vaporizer liquid inlet valve, allowing LNG to directly enter the self-pressurizing vaporizer, and after vaporization, enter the LNG storage tank. At this time, closely observe the pressure, and when the pressure of the LNG storage tank reaches the required value, close the valve of the pressurized liquid phase valve.

2. Precautions:

(1) During the operation of the LNG full containment tank, ensure that the upper liquid level is 90% and the lower limit is 15%.

(2) When manually operating the pressurization system, it is strictly prohibited to leave the site.

(3) When the pressurization system is in operation, the depressurization system should be closed.

(4) During manual operation, it is strictly prohibited to leave the site.

4. Risk Analysis and Countermeasures

1. When loading and unloading LNG ships, operators should wear masks, anti-static work clothes, and anti-freeze gloves.

2. When unloading LNG tank trucks, it is prohibited to move vehicles to avoid breaking the loading and unloading hose, causing a large amount of LNG leakage.

3. When there is LNG in the pipeline, the valves at both ends cannot be closed at the same time.

4. It is prohibited to touch or step on low-temperature pipelines and facilities.

5. Under no circumstances should water, oil, mechanical impurities, etc. enter the pipeline to avoid clogging the pipeline.

LNG full containment tank

Related

The tank’s robust design provides solid support for the green transformation of shipping! A vessel equipped with Dürr marine fuel tanks has successfully been launched and undergone sea trials.

On July 30, 2026, an inland vessel equipped with Dürr‑customized marine fuel tanks was successfully launched and officially commenced comprehensive sea trials. This new vessel represents another practical milestone in the low‑carbon transformation of inland shipping, while also fully validating Dürr’s superior product quality, end-to-end support services, and efficient project execution and delivery capabilities—setting a high‑standard benchmark for the large‑scale supply of clean‑energy propulsion systems to domestic inland vessels.

2026-07-31

Mayor Liu paid a visit to Nanyang’s Duer Equipment for an inspection and research tour, encouraging the company to deepen its expertise in the cryogenic equipment sector and to bolster the high-quality development of Nanyang’s manufacturing industry.

On July 20, Mayor Liu of Nanyang City and his delegation paid a field visit to Nanyang Dürr Gas Equipment Co., Ltd. (Dürr Equipment), conducting an in-depth inspection of the company’s production and operations, technological innovation, industrial-chain development, and workplace safety. Relevant leaders from Sheqi County and the enterprise’s management accompanied the group throughout the visit.

2026-07-21

Heartwarming Dragon Boat Festival Brings Warmth to All; United in Purpose, Moving Forward Together | Dur Equipment Distributes Dragon Boat Festival Benefits to All Employees

The fragrant aroma of zongzi leaves heralds the arrival of the Dragon Boat Festival, filling the workplace with warmth and heartfelt care. As this cherished traditional Chinese holiday approaches, Du’er Equipment has meticulously planned and thoughtfully organized a series of initiatives to celebrate and promote China’s rich cultural heritage, extend genuine corporate关怀, and express gratitude for the dedicated efforts of all employees. By strengthening team cohesion and fostering a stronger sense of belonging, Du’er Equipment has extended thoughtful, generous festival benefits and sincere holiday greetings to every employee on duty.

2026-06-18

County Party Secretary Guan Wenbo paid a visit to Dur Equipment to conduct research and provide guidance.

Recently, Secretary Guan of the Sheqi County Party Committee and his delegation visited the production workshop of Nanyang Duer Gas Equipment Co., Ltd. to conduct an on-site inspection of the company’s operations, technological innovation, and project progress. They listened carefully to the enterprise’s concerns, promptly addressed the challenges and issues it faces, and injected confidence and momentum into its drive for high-quality development.

2026-05-18

Doer's tank container products have been officially shipped overseas

With the continuous growth in global demand for cross-border logistics of cryogenic liquids and industrial gases, the tank container products independently developed and produced by Doer Equipment officially commenced shipment today, bound for overseas markets. Leveraging its excellent pressure-bearing performance, comprehensive auxiliary equipment, and safe and reliable structural design, this product will provide overseas customers with efficient and compliant transportation solutions for cryogenic liquefied gases.

2026-04-06

Duer Equipment Lights Up a New Ecosystem for Inland Waterway Shipping with LNG Fuel Tanks

As the philosophy of “Lucid waters and lush mountains are invaluable assets” takes root in the arteries of industry, green shipping is emerging as the core engine driving high-quality development of inland economic belts. Driven strongly by the nation’s policies on new-energy vessels, the market for inland new-energy ships is entering a golden period of rapid growth. On the Xijiang waterway in Guangxi, vessels equipped with LNG fuel tanks supplied by Nanyang Durr Gas Equipment Co., Ltd. are harnessing clean power to paint an ecological picture of “clear waters flowing smoothly.”

2025-11-27