Oxygen, Nitrogen, and Argon Storage TankComposed of a vacuum shell and a pressure vessel placed within. The oxygen, nitrogen, and argon storage tank can operate under low to medium pressure according to actual design requirements. It is equipped with a safety rupture device, which ensures safe protection of the storage tank in case of overpressure. The storage tank is designed to be safe, reliable in operation, and sturdy. When operating the tank, strictly adhere to the correct safety and operational regulations.

Charging Precautions
Pre-charging is usually prepared for a "warm tank." The so-called "warm tank" refers to something that has not been used before charging, to ensure the purity of the storage medium.
The blowing pressure should be less than 50% of the tank's working pressure or 0.2 MPa, and a positive pressure of 0.03 MPa should always be maintained inside the tank. This prevents pollutants from the atmosphere from being re-absorbed into the tank.
Pre-charging (Warm Storage Tank) Plan
1. Blow the storage tank to ensure the purity of the storage medium.
2. Clearly identify the substances contained in the transport device that are to be accurately transported.
3. Ensure that all valves, except for the liquid level indicating liquid flow valve and the liquid level indicating valve, are closed.
Connect the delivery hose of the conveyor to the tank charging port.
Operational Preparation
Oxygen, Nitrogen, and Argon Storage TankOperational preparation includes adjusting the pressure regulating valve and opening the pressure regulating circuit. Automatically evaporate the liquid and deliver the gas required for the charging device.
Tank Pressure Control
The pressure of the tank is controlled by a regulating valve, and the working pressure can be adjusted through the adjustment handle at the bottom of the regulating valve without disassembling any parts.
Charging
The tank in use is recharged through the charging valves at the top and bottom. Since the hot vapor on the liquid is compressed, bottom charging will cause the tank pressure to rise. If the correct charging procedure is followed, no failures will occur during use or transportation. Generally, it is not necessary to release the tank pressure before charging.
Note: Charging a low-temperature tank from the bottom will compress the MOIN gas in the evaporative space, increasing the tank pressure, while charging from the top will reduce the pressure. This is because the top space cools the MOIN gas and re-liquefies it.
1. Clearly identify that the substances in the conveyor are indeed the substances being transported.
2. Ensure that the top and bottom charging valves are closed.
3. Ensure that the tank is at the specified operating pressure.
4. Please ensure that all other valves are in normal working condition.
5. Connect the conveyor hose to the tank charging port.
Note: Before charging, open the discharge valve of the charging pipe and the gas delivery valve for about 3 minutes, or until the hose starts to frost, to cool the water delivery pipeline and flush it. Close the discharge valve of the charging pipe.
Oxygen, nitrogen, and argon storage tank
Related
Duer Equipment Lights Up a New Ecosystem for Inland Waterway Shipping with LNG Fuel Tanks
As the philosophy of “Lucid waters and lush mountains are invaluable assets” takes root in the arteries of industry, green shipping is emerging as the core engine driving high-quality development of inland economic belts. Driven strongly by the nation’s policies on new-energy vessels, the market for inland new-energy ships is entering a golden period of rapid growth. On the Xijiang waterway in Guangxi, vessels equipped with LNG fuel tanks supplied by Nanyang Durr Gas Equipment Co., Ltd. are harnessing clean power to paint an ecological picture of “clear waters flowing smoothly.”
2025-11-27
On March 8, 2024, a milestone moment took place in the conference room on the fourth floor of Nanyang Doerr—the launch meeting for the Operations Management System project, co-hosted by Nanyang Doer and Zhongxu Education, was grandly held here. After in-depth interviews and careful preparations in the early stages, both parties have embarked on a new chapter of cooperation.
2024-03-08
The autumn is crisp and refreshing, with the fragrance of golden osmanthus in the air. On September 28, 2022, after intensive preparations, the intelligent production workshop project of the second phase of Nanyang Duer Gas Equipment Co., Ltd. officially entered the construction phase, marking the beginning of a high-tech intelligent production base. On this fertile land, the momentum is grand, and everything indicates a new vitality for the future of this land.
2022-09-28
Mid-Autumn Festival Charity: Deep Respect for the Elderly
On the morning of September 11, 2022, caring individuals from Nanyang visited the Le Ru Jia Elderly Service Center to offer Mid-Autumn Festival greetings.
2022-09-11
Devote love, great love knows no boundaries.
On the afternoon of September 5, 2022, Nanyang Du'er Gas Equipment Co., Ltd. donated to the 99 Charity Day event at the Civil Affairs Bureau of Sheqi County.
2022-09-06